Connecticut senator seeks answers on Y2K readiness of Millstone nuclear power plant

greenspun.com : LUSENET : TimeBomb 2000 (Y2000) : One Thread

http://www.computerworld.com/home/news.nsf/all/9911302nuke

Connecticut senator seeks answers on Y2K readiness of Millstone nuclear power plant

By Linda Rosencrance

U.S. Sen. Christopher J. Dodd (D-Conn.) today asked Northeast Utilities and the Nuclear Regulatory Commission (NRC) to provide him with specific information on the measures they've taken to ensure that Northeast's Millstone nuclear power pant in Connecticut is ready for the year 2000 date change.

In letters to the utility and the commission, Dodd said he'd heard from a number of constituents expressing anxiety about the Y2K problem and its potential impact on plant safety. He said constituents told him about protests at Millstone by people concerned that safety at plant will be compromised because of Y2K problems.

Dodd added that he's concerned that the plant's biennial emergency drill was postponed from September of this year to March 2000.

Dodd asked for responses to his letters by Dec. 6.

"...[G]iven the potential harm even one nuclear accident can cause, I want to be especially clear about the need for added vigilance at this time. Heightened public anxiety about the large number of unknown factors means that even those regulators and industries which put a premium on public safety at all times must be especially sensitive to the Y2K issue," Dodd said in his letters.

However, the NRC has already said that all 103 power plants it regulates are Y2K-ready. NRC spokeswoman Diane Screnci said the agency's Web site has information about the steps it has taken to make sure all the nuclear power plants are ready for Y2K, although she said there isn't specific information about each plant.

Terrence McIntosh, a spokesman for Northeast Utilities, said Millstone is Y2K-ready and that the utility had sent out press release to various media outlets to alert them to that fact. He added that the postponed drill had nothing to do with Y2K -- although the utility has conducted Y2K preparedness drills at Millstone -- but was a regularly scheduled emergency drill.

"Sen. Dodd is responding to his constituents. But here we have some antinuclear groups whose agendas are to shut down the plant," McIntosh said. "Millstone has been Y2K-ready since June 30, 1999. We have participated in several Y2K-specific drills.The NRC asked some utilities to postpone their regularly scheduled emergency drills because it did not have enough staff to monitor all the drills."

McIntosh said the utility's chairman, Michael Morris, will respond to Dodd in a letter with specific information by Dec. 6. The utility company is headquartered in West Springfield, Mass.

-- Uncle Bob (UNCLB0B@Tminus31&counting.down), November 30, 1999

Answers

God Bless Sen. Dodd.

Here in my area, TXU's web page lists their business and administrative systems as "Y2K Compliant". They list Comanche Peaks 1 & 2 (nuclear plants) as "Y2K Ready."

Their difference of terms, not mine. Senators Gramm and Hutchinson are welcome to step right up to the plate.

-- mommacarestx (nospam@thanks.com), November 30, 1999.


"Dodd added that he's concerned that the plant's biennial emergency drill was postponed from September of this year to March 2000."

LOL LOL LOL LOL glowing toast

-- slippage (millennium@2001.whenever), November 30, 1999.


Mama: Our Senator Gramm does not believe anything will happen. If Senator Hutchinson has any thoughts on the subject, she has kept them to herself. I am seven air miles from Commanche Peak and my TXU friends who live all around me say everything is OK. I will still have my iodate pills handy and my suburban loaded on 12/31/99 as a backup plan.

-- Neil G.Lewis (pnglewis1@yahoo.com), November 30, 1999.

After almost 20 years of following my husband around from nuclear new construction site, throught outages/shutdowns, etc., and now living in that wonderful state of Connecticut at a site about as far away from Millstone as one can be and still be in Conn., one thing I know for sure: Northeast Utilities really sucks compared to Con Ed, NYSGE, Central Hudson, at least from a consumers point of view. In the year and half that we have been hear, we have lost power 10 times, once for 4 days. Maybe a small thing, but the other utilities I mentioned were terrific compared to NU. Could this micro view mean anything in regards to how NU runs Millstone? I wonder where Dodd will be hanging out the first few weeks of January. Aspen, perhaps, or out with Imus at his ranch?

-- Itinerant Nuclear Worker (dromano03@snet.com), November 30, 1999.

N. Lewis et al.:

Shortly before rollover, I will be monitoring prevailing winds closely.

I'm 80 miles from South Texas Project....

-- Mr. Bob (thebobster@delphi.com), November 30, 1999.



Neil Lewis,

Keeping close eye on Commanche Peak status for past two years. My wife's family also within 15 mile circle. Although one of newest facilities in country, contractor took too many shortcuts during construction, with inferior materials I understand. Three Mile Island was not a fun ride for me in '79 at mile 17. Best Wishes from Alaska!

-- (snowleopard6@webtv.net), December 01, 1999.